Günöz Textile

18.02.2022
10.474 view
Günöz Textile
Location
  • Velimeşe, Çorlu / Tekirdağ
The Work Done
  • 2000 kVA H.G. switchgear assembly and installation
  • 2000 kVA main distribution and compensation panel and installation
  • 1000 kVA main distribution and compensation panel and installation
  • 1000 kVAr harmonic filtration panel and installation
  • 1450 kW cogeneration system installation and commissioning
  • 630 A – 1000 A busbar transmission line installation
  • 600 kW PLC based load shedding automation system
  • Factory high current, low current, lighting and electrification operations
  • Engineering services